Braddock Avenue-Kenmawr Avenue Ramp Replacement
Overview
- Location: At and near the Braddock Avenue/Kenmawr Avenue ramp, which is located between Talbot Avenue and Line Street in Rankin
- Current traffic restrictions: The Talbot Avenue ramp, located between the Braddock Avenue/Kenmawr Avenue/Talbot Avenue intersection and Fleet Street, will close starting at 9 a.m. on Monday, April 7. Also, Kenmawr Avenue will be reduced to a single lane of traffic in each direction between Carrie Furnace Boulevard and Braddock Avenue.
- Project start date: March 4, 2023
- Estimated traffic restrictions end date: November 2025
- Scope of work: Replacement of the Braddock Avenue/Kenmawr ramp, repairs to a Rankin Bridge ramp (Rankin/Braddock exit), and reconstruction of the Braddock Avenue/Kenmawr Avenue/Talbot Avenue intersection. That includes new pavement, sidewalk, curb, drainage, barrier and guide rail, traffic signals, roadway lighting, signage, and pavement markings.
- Primary contractor: Mosites Construction Company
- Estimated cost: $9.3 million
Overview
- Location: At and near the Braddock Avenue/Kenmawr Avenue ramp, which is located between Talbot Avenue and Line Street in Rankin
- Current traffic restrictions: The Talbot Avenue ramp, located between the Braddock Avenue/Kenmawr Avenue/Talbot Avenue intersection and Fleet Street, will close starting at 9 a.m. on Monday, April 7. Also, Kenmawr Avenue will be reduced to a single lane of traffic in each direction between Carrie Furnace Boulevard and Braddock Avenue.
- Project start date: March 4, 2023
- Estimated traffic restrictions end date: November 2025
- Scope of work: Replacement of the Braddock Avenue/Kenmawr ramp, repairs to a Rankin Bridge ramp (Rankin/Braddock exit), and reconstruction of the Braddock Avenue/Kenmawr Avenue/Talbot Avenue intersection. That includes new pavement, sidewalk, curb, drainage, barrier and guide rail, traffic signals, roadway lighting, signage, and pavement markings.
- Primary contractor: Mosites Construction Company
- Estimated cost: $9.3 million
-
March 24, 2025
Share March 24, 2025 on Facebook Share March 24, 2025 on Twitter Share March 24, 2025 on Linkedin Email March 24, 2025 linkThe Talbot Avenue ramp in Rankin will close starting at 9 a.m. on Monday, April 7, 2025. The ramp is located between the Braddock Avenue/Kenmawr Avenue/Talbot Avenue intersection and Fleet Street. Also, Kenmawr Avenue will be reduced to a single lane of traffic in each direction between Carrie Furnace Boulevard and Braddock Avenue. Those restrictions are expected to end in November 2025. They are required for the reconstruction of the Braddock Avenue/Kenmawr Avenue/Talbot Avenue intersection.
Traffic will be detoured using Braddock Avenue and Fourth Street.
-
December 19, 2024
Share December 19, 2024 on Facebook Share December 19, 2024 on Twitter Share December 19, 2024 on Linkedin Email December 19, 2024 linkThe Braddock Avenue/Kenmawr Avenue ramp, located between Talbot Avenue and Line Street in Rankin, has reopened to traffic. Also, Fleet Street between Maple Way and West Braddock Avenue, Maple Way between Fleet Street and Pattison Avenue, and Line Street have reopened to traffic.
Additional work at the Braddock Avenue/Kenmawr Avenue/Talbot Avenue intersection and permanent pavement markings, including those used for bike lanes, will be completed as part of the project next year. That will require a closure of the Talbot Avenue ramp between Braddock Avenue/Kenmawr Avenue and Fleet Street as well as closure of the southbound lane of Kenmawr Avenue between Carrie Furnace Boulevard and Braddock Avenue.
The exact start date for those traffic restrictions has yet to be determined. When plans are finalized, that information will be provided to the public. The restrictions are expected to end during fall 2025.
-
December 17, 2024
Share December 17, 2024 on Facebook Share December 17, 2024 on Twitter Share December 17, 2024 on Linkedin Email December 17, 2024 linkA Rankin Bridge ramp (Rankin/Braddock exit) between South Braddock Avenue and Kenmawr Avenue/Braddock Avenue in Rankin has reopened to traffic. A lane closure on Kenmawr Avenue between Carrie Furnace Boulevard and Braddock Avenue has also ended.
The Braddock Avenue/Kenmawr Avenue ramp, Fleet Street between West Braddock Avenue and Maple Way, Maple Way between Fleet Street and Pattison Avenue, and Line Street are expected to reopen later in December.
-
September 22, 2024
Share September 22, 2024 on Facebook Share September 22, 2024 on Twitter Share September 22, 2024 on Linkedin Email September 22, 2024 linkThe Braddock Avenue/Kenmawr Avenue ramp replacement project has reached a significant milestone. Crews are pouring the ramp’s concrete deck, which is what people will drive on when the new ramp opens later this year. Almost 400 cubic yards of concrete is being used to construct the deck – enough to fill more than 30 concrete mixer trucks.
The project remains on schedule.
-
July 23, 2024
Share July 23, 2024 on Facebook Share July 23, 2024 on Twitter Share July 23, 2024 on Linkedin Email July 23, 2024 linkThe Braddock Avenue/Kenmawr Avenue ramp replacement project reached a significant milestone, as the new ramp's steel beams were placed on the reconstructed abutments and new piers.
Amelie Construction & Supply, a subcontractor for the primary construction contractor Mosites Construction Company, used an 18,400-pound, 115-foot crane to place the beams, which ranged from 80 to 120 feet in length and weighed between 20,565 to 35,525 pounds. The beams were fabricated and driven from Lancaster, PA. The project remains on schedule.
-
June 7, 2024
Share June 7, 2024 on Facebook Share June 7, 2024 on Twitter Share June 7, 2024 on Linkedin Email June 7, 2024 linkA Rankin Bridge ramp (Rankin/Braddock exit) between South Braddock Avenue and Kenmawr Avenue/Braddock Avenue in Rankin will close starting at 6 a.m. on Monday, June 17, 2024. Also, Kenmawr Avenue will be reduced to a single lane of traffic in each direction between Carrie Furnace Boulevard and Braddock Avenue. Those restrictions are expected to end in December 2024.
For the ramp closure, eastbound car traffic will be detoured using South Braddock Avenue, Kenmawr Avenue, Talbot Avenue, Fourth Street, and Sixth Street. Westbound car traffic will be detoured using Sixth Street, Talbot Avenue, Fourth Street, and Kenmawr Avenue. Truck traffic will be detoured using South Braddock Avenue, I-376, Ardmore Boulevard (Route 30), Electric Avenue, and Braddock Avenue.
-
April 8, 2024
Share April 8, 2024 on Facebook Share April 8, 2024 on Twitter Share April 8, 2024 on Linkedin Email April 8, 2024 linkLine Street in Rankin will close at 9 a.m. on Monday, April 15, 2024. The closure is expected to end in December 2024.
Line Street vehicle and pedestrian traffic will be detoured using Fleet Street, Holland Avenue, and Second Street.
Who's Listening
-
Phone 412-350-2451 Email brent.wasko@alleghenycounty.us
Project Milestones
-
Close Braddock Avenue/Kenmawr Avenue ramp, Fleet Street between West Braddock Avenue and Maple Way, and Maple Way between Fleet Street and Pattison Avenue
Braddock Avenue-Kenmawr Avenue Ramp Replacement has finished this stage -
Start demolishing Braddock Avenue/Kenmawr Avenue ramp
Braddock Avenue-Kenmawr Avenue Ramp Replacement has finished this stage -
Close Line Street
Braddock Avenue-Kenmawr Avenue Ramp Replacement has finished this stage -
Start constructing Braddock Avenue/Kenmawr Avenue ramp piers
Braddock Avenue-Kenmawr Avenue Ramp Replacement has finished this stage -
Start erecting Braddock Avenue/Kenmawr Avenue ramp steel structure
Braddock Avenue-Kenmawr Avenue Ramp Replacement has finished this stage -
Close Rankin Bridge ramp (Rankin/Braddock exit)
Braddock Avenue-Kenmawr Avenue Ramp Replacement has finished this stage -
Start reconstruction of the Braddock Avenue/Kenmawr Avenue/Talbot Avenue intersection
Braddock Avenue-Kenmawr Avenue Ramp Replacement has finished this stage -
Start installation of traffic safety features, drainage, signals, and lighting
Braddock Avenue-Kenmawr Avenue Ramp Replacement has finished this stage -
Start placement of Braddock Avenue/Kenmawr Avenue ramp deck
Braddock Avenue-Kenmawr Avenue Ramp Replacement has finished this stage -
Reopen Rankin Bridge ramp
Braddock Avenue-Kenmawr Avenue Ramp Replacement has finished this stage -
Reopen Braddock Avenue/Kenmawr Avenue ramp, Fleet Street, Maple Way, and Line Street
Braddock Avenue-Kenmawr Avenue Ramp Replacement has finished this stage -
Winter shutdown
Braddock Avenue-Kenmawr Avenue Ramp Replacement has finished this stage -
Close Talbot Avenue ramp
Braddock Avenue-Kenmawr Avenue Ramp Replacement has finished this stage -
Restart reconstruction of the Braddock Avenue/Kenmawr Avenue/Talbot Avenue intersection
Braddock Avenue-Kenmawr Avenue Ramp Replacement is currently at this stage -
Start installation of permanent pavement markings, including turn arrows, crosswalks, and bike lanes
this is an upcoming stage for Braddock Avenue-Kenmawr Avenue Ramp Replacement -
Reopen Talbot Avenue ramp
this is an upcoming stage for Braddock Avenue-Kenmawr Avenue Ramp Replacement
Photos
Videos
-
Click here to play video Braddock Avenue/Kenmawr Avenue Ramp Deck Pour The Braddock Avenue/Kenmawr Avenue ramp replacement project reached a significant milestone. Crews are pouring the ramp’s concrete deck, which is what people will drive on when the new ramp opens later this year. Almost 400 cubic yards of concrete is being used to construct the deck – enough to fill more than 30 concrete mixer trucks.