July 23, 2024

The Braddock Avenue/Kenmawr Avenue ramp replacement project reached a significant milestone, as the new ramp's steel beams were placed on the reconstructed abutments and new piers.

Amelie Construction & Supply, a subcontractor for the primary construction contractor Mosites Construction Company, used an 18,400-pound, 115-foot crane to place the beams, which ranged from 80 to 120 feet in length and weighed between 20,565 to 35,525 pounds. The beams were fabricated and driven from Lancaster, PA. The project remains on schedule.

Share July 23, 2024 on Facebook Share July 23, 2024 on Twitter Share July 23, 2024 on Linkedin Email July 23, 2024 link
#<Object:0x000000001e36c270>