Overview
Location: Jacks Run Road over I-279 and between Bellevue Road/Bellpark Drive and Kane Lane
Traffic restrictions: Full closure of Jacks Run Road between Bellevue Road/Bellpark Drive and Kane Lane. Periodic full closures of I-279 northbound and southbound – along with the interstate’s High Occupancy Vehicle (HOV) lanes – from June 22 through August between the following times:
9 pm to 5 am Sunday-Friday
9 pm Friday to 9am Saturday
9 pm Saturday to 9 am Sunday
I-279 northbound will be closed between the McKnight Road/Evergreen Road exit ramp (Exit 4) and the I-279 North entrance ramp from Camp Horne Road. I-279 southbound will be closed between the Camp Horne Road exit ramp (Exit 8) and the I-279 South entrance ramp from McKnight Road.
When I-279 is not fully closed, there will continue to be periodic single-lane closures on I-279 northbound and southbound under Jacks Run Road and closure of the I-279 northbound on-ramp from Cemetery Lane between 7 pm and 6 am daily through the remainder of the project.
Demolition project start date: April 27, 2026
Estimated demolition project end date: September 2026
New bridge construction start date: Winter/Spring 2027
Estimated new bridge construction end date: Fall 2027
Scope of work: Demolition and replacement of Jacks Run Bridge No. 3
Primary contractor for demolition: Swank Construction Company
Estimated cost of demolition: $2.8 million
Primary contractor for new bridge construction: TBD
Estimated cost of new bridge construction: TBD
Jacks Run Road Detour
Southbound toward Brighton Road
From Bellevue Road, stay straight as the road becomes North Balph Avenue
Turn right onto Lincoln Avenue
Turn right onto Brighton Road
Turn right onto Jacks Run Road (if needed)
Northbound toward Bellevue Road
Same as the southbound detour in the opposite direction
I-279 Northbound Detour
From I-279 northbound, take Exit 4 (McKnight Road/Evergreen Road)
Use the left lane to exit toward McKnight Road
Take the West View/Millvale exit on the right
Turn right onto Babcock Boulevard
Turn left onto Rochester Road
Turn left onto Lowries Run Road
Stay straight as the road becomes Camp Horne Road
Turn right onto the I-279 North on-ramp
Union Avenue to I-279 Northbound Detour
From Union Avenue, stay straight as the road becomes Gass Road
Turn right onto Highland Avenue
Turn left onto Perry Highway
Turn left onto Rochester Road
Turn left onto Lowries Run Road
Stay straight as the road becomes Camp Horne Road
Turn right onto the I-279 North on-ramp/li>
Cemetery Lane to I-279 Northbound Detour
From Cemetery Lane, turn onto Perry Highway
Turn left onto Rochester Road
Turn left onto Lowries Run Road
Stay straight as the road becomes Camp Horne Road
Turn right onto the I-279 North on-ramp
Overview
Location: Jacks Run Road over I-279 and between Bellevue Road/Bellpark Drive and Kane Lane
Traffic restrictions: Full closure of Jacks Run Road between Bellevue Road/Bellpark Drive and Kane Lane. Periodic full closures of I-279 northbound and southbound – along with the interstate’s High Occupancy Vehicle (HOV) lanes – from June 22 through August between the following times:
9 pm to 5 am Sunday-Friday
9 pm Friday to 9am Saturday
9 pm Saturday to 9 am Sunday
I-279 northbound will be closed between the McKnight Road/Evergreen Road exit ramp (Exit 4) and the I-279 North entrance ramp from Camp Horne Road. I-279 southbound will be closed between the Camp Horne Road exit ramp (Exit 8) and the I-279 South entrance ramp from McKnight Road.
When I-279 is not fully closed, there will continue to be periodic single-lane closures on I-279 northbound and southbound under Jacks Run Road and closure of the I-279 northbound on-ramp from Cemetery Lane between 7 pm and 6 am daily through the remainder of the project.
Demolition project start date: April 27, 2026
Estimated demolition project end date: September 2026
New bridge construction start date: Winter/Spring 2027
Estimated new bridge construction end date: Fall 2027
Scope of work: Demolition and replacement of Jacks Run Bridge No. 3
Primary contractor for demolition: Swank Construction Company
Estimated cost of demolition: $2.8 million
Primary contractor for new bridge construction: TBD
Estimated cost of new bridge construction: TBD
Jacks Run Road Detour
Southbound toward Brighton Road
From Bellevue Road, stay straight as the road becomes North Balph Avenue
Turn right onto Lincoln Avenue
Turn right onto Brighton Road
Turn right onto Jacks Run Road (if needed)
Northbound toward Bellevue Road
Same as the southbound detour in the opposite direction
I-279 Northbound Detour
From I-279 northbound, take Exit 4 (McKnight Road/Evergreen Road)
Use the left lane to exit toward McKnight Road
Take the West View/Millvale exit on the right
Turn right onto Babcock Boulevard
Turn left onto Rochester Road
Turn left onto Lowries Run Road
Stay straight as the road becomes Camp Horne Road
Turn right onto the I-279 North on-ramp
Union Avenue to I-279 Northbound Detour
From Union Avenue, stay straight as the road becomes Gass Road
Share Where will the debris from the bridge be discarded, will it be to the right of the highway right before the West View/Bellevue exit? on FacebookShare Where will the debris from the bridge be discarded, will it be to the right of the highway right before the West View/Bellevue exit? on X (formerly Twitter)Share Where will the debris from the bridge be discarded, will it be to the right of the highway right before the West View/Bellevue exit? on LinkedinEmail Where will the debris from the bridge be discarded, will it be to the right of the highway right before the West View/Bellevue exit? link
Where will the debris from the bridge be discarded, will it be to the right of the highway right before the West View/Bellevue exit?
Gary
asked
4 months ago
The county’s contractor will be removing all debris from the site to an approved waste location with the exception of the topsoil that is currently being stored along the interstate. That topsoil will remain there until it is reused in the median after a new Jacks Run Bridge No. 3 is constructed next year.
Share Jacks Run Road leading up to the closed bridge has had many spot repairs for water line breaks, etc. There are numerous spots that seem to be forming sink holes and the road is just in bad shape. Is there a plan to fix it prior to the bridge reopening? on FacebookShare Jacks Run Road leading up to the closed bridge has had many spot repairs for water line breaks, etc. There are numerous spots that seem to be forming sink holes and the road is just in bad shape. Is there a plan to fix it prior to the bridge reopening? on X (formerly Twitter)Share Jacks Run Road leading up to the closed bridge has had many spot repairs for water line breaks, etc. There are numerous spots that seem to be forming sink holes and the road is just in bad shape. Is there a plan to fix it prior to the bridge reopening? on LinkedinEmail Jacks Run Road leading up to the closed bridge has had many spot repairs for water line breaks, etc. There are numerous spots that seem to be forming sink holes and the road is just in bad shape. Is there a plan to fix it prior to the bridge reopening? link
Jacks Run Road leading up to the closed bridge has had many spot repairs for water line breaks, etc. There are numerous spots that seem to be forming sink holes and the road is just in bad shape. Is there a plan to fix it prior to the bridge reopening?
Courtney S
asked
5 months ago
Hi, Courtney. We appreciate you reaching out. We're going to assign this to our maintenance staff to investigate. In case they have any questions, would you please provide your name, phone number, and/or email address to brent.wasko@alleghenycounty.us? Thank you!
Jacks Run Bridge No. 3 Replacement Projects has finished this stage
July 3, 2025
Bridge Demolition Work Advertised for Bids
Jacks Run Bridge No. 3 Replacement Projects has finished this stage
Winter 2026
Daily periodic single-lane closures on I-279 northbound and southbound under Jacks Run Road and closure of I-279 northbound on-ramp from Cemetery Lane between 7 pm and 6 am begin
Jacks Run Bridge No. 3 Replacement Projects has finished this stage
April 27, 2026
Start of Bridge Demolition
Jacks Run Bridge No. 3 Replacement Projects has finished this stage
April 27, 2026
Daily periodic single-lane closures on I-279 northbound and southbound under Jacks Run Road and HOV lane closures between 7 pm and 3 pm implemented
Jacks Run Bridge No. 3 Replacement Projects has finished this stage
May 31, 2026 through Friday, June 5
Periodic closures of I-279 northbound and southbound between McKnight Road and Camp Horne Road and HOV lanes between 9 am and 5 am Sunday-Friday, 9 pm Friday to 9 am Saturday, and 9 pm Saturday to 9 am Sunday begin
Jacks Run Bridge No. 3 Replacement Projects has finished this stage
June 22, 2026
Bridge Construction Work Advertised for Bids
Jacks Run Bridge No. 3 Replacement Projects has finished this stage
August 13, 2026
End of Bridge Demolition
Jacks Run Bridge No. 3 Replacement Projects is currently at this stage
September 2026
Start of New Bridge Construction
this is an upcoming stage for Jacks Run Bridge No. 3 Replacement Projects
Winter/Spring 2027
New Bridge Opens