Homestead Grays Bridge Repairs Project

Share Homestead Grays Bridge Repairs Project on Facebook Share Homestead Grays Bridge Repairs Project on X (formerly Twitter) Share Homestead Grays Bridge Repairs Project on Linkedin Email Homestead Grays Bridge Repairs Project link

Consultation has concluded

Overview

Location: Homestead Grays Bridge in Pittsburgh and Homestead

Traffic restriction: Two of the four lanes on the Homestead Grays Bridge will be closed from 9 p.m. on Wednesday, October 21 through 6 a.m. on Thursday, October 22. Two of the four lanes will close again from 9 p.m. on Thursday, October 22 through 6 a.m. on Monday, October 26. Afterward, there will be periodic overnight lane closures at various locations on the bridge between 9 p.m. on Fridays to 6 a.m. on Mondays

Project start date: October 2, 2026

Estimated project end date: November 8, 2026

Scope of work: Bridge span, pier, and deck repairs

Primary construction contractor: Pugliano Construction

Estimated cost: $902,594

Overview

Location: Homestead Grays Bridge in Pittsburgh and Homestead

Traffic restriction: Two of the four lanes on the Homestead Grays Bridge will be closed from 9 p.m. on Wednesday, October 21 through 6 a.m. on Thursday, October 22. Two of the four lanes will close again from 9 p.m. on Thursday, October 22 through 6 a.m. on Monday, October 26. Afterward, there will be periodic overnight lane closures at various locations on the bridge between 9 p.m. on Fridays to 6 a.m. on Mondays

Project start date: October 2, 2026

Estimated project end date: November 8, 2026

Scope of work: Bridge span, pier, and deck repairs

Primary construction contractor: Pugliano Construction

Estimated cost: $902,594

Consultation has concluded

Please let us know if you have any questions or concerns about the Homestead Grays Bridge Repairs Project.

  • Share Will the steel roadway plates be removed? The "clunking" noise of vehicles traveling over plates can be heard day and night here on 3300 block of Shady Avenue. on Facebook Share Will the steel roadway plates be removed? The "clunking" noise of vehicles traveling over plates can be heard day and night here on 3300 block of Shady Avenue. on X (formerly Twitter) Share Will the steel roadway plates be removed? The "clunking" noise of vehicles traveling over plates can be heard day and night here on 3300 block of Shady Avenue. on Linkedin Email Will the steel roadway plates be removed? The "clunking" noise of vehicles traveling over plates can be heard day and night here on 3300 block of Shady Avenue. link

    Will the steel roadway plates be removed? The "clunking" noise of vehicles traveling over plates can be heard day and night here on 3300 block of Shady Avenue.

    General asked 13 days ago

    The Homestead Grays Bridge repairs project is expected to end earlier than originally expected. If the weather cooperates, our contractor will complete its work this weekend. At that point, there will be no steel plates on the bridge.

  • Share Hello! I have basically no issues with this project, but I do have one gripe (likely due to my lack of sleep and growing lack of patience as I sit in traffic). I live two block up from the end of the bridge on 9th Ave. I knew bridge traffic started at 9pm, so I thought I was fine to go across the bridge instead of taking an alternative route that would’ve taken me long to get home. However, I’m now wishing I did the opposite, as I’ve been sitting in traffic since 7:15, and it is now 8:15. I get work needs to be done to keep the bridge safe, but I feel as though it might be helpful to increase times on green lights heading towards the Waterfront area. Also, it’s not 9, so I’m not sure why it’s down to one lane right now; is there an email chain I can be on to know when the lanes will be closed prior to 9pm on Fridays (once again, it’s 8:15pm on a Thursday, and I’m a little irked by this)? Best of luck to complete this project safely and rather quickly (hopefully before the intended end date). Best, Katie on Facebook Share Hello! I have basically no issues with this project, but I do have one gripe (likely due to my lack of sleep and growing lack of patience as I sit in traffic). I live two block up from the end of the bridge on 9th Ave. I knew bridge traffic started at 9pm, so I thought I was fine to go across the bridge instead of taking an alternative route that would’ve taken me long to get home. However, I’m now wishing I did the opposite, as I’ve been sitting in traffic since 7:15, and it is now 8:15. I get work needs to be done to keep the bridge safe, but I feel as though it might be helpful to increase times on green lights heading towards the Waterfront area. Also, it’s not 9, so I’m not sure why it’s down to one lane right now; is there an email chain I can be on to know when the lanes will be closed prior to 9pm on Fridays (once again, it’s 8:15pm on a Thursday, and I’m a little irked by this)? Best of luck to complete this project safely and rather quickly (hopefully before the intended end date). Best, Katie on X (formerly Twitter) Share Hello! I have basically no issues with this project, but I do have one gripe (likely due to my lack of sleep and growing lack of patience as I sit in traffic). I live two block up from the end of the bridge on 9th Ave. I knew bridge traffic started at 9pm, so I thought I was fine to go across the bridge instead of taking an alternative route that would’ve taken me long to get home. However, I’m now wishing I did the opposite, as I’ve been sitting in traffic since 7:15, and it is now 8:15. I get work needs to be done to keep the bridge safe, but I feel as though it might be helpful to increase times on green lights heading towards the Waterfront area. Also, it’s not 9, so I’m not sure why it’s down to one lane right now; is there an email chain I can be on to know when the lanes will be closed prior to 9pm on Fridays (once again, it’s 8:15pm on a Thursday, and I’m a little irked by this)? Best of luck to complete this project safely and rather quickly (hopefully before the intended end date). Best, Katie on Linkedin Email Hello! I have basically no issues with this project, but I do have one gripe (likely due to my lack of sleep and growing lack of patience as I sit in traffic). I live two block up from the end of the bridge on 9th Ave. I knew bridge traffic started at 9pm, so I thought I was fine to go across the bridge instead of taking an alternative route that would’ve taken me long to get home. However, I’m now wishing I did the opposite, as I’ve been sitting in traffic since 7:15, and it is now 8:15. I get work needs to be done to keep the bridge safe, but I feel as though it might be helpful to increase times on green lights heading towards the Waterfront area. Also, it’s not 9, so I’m not sure why it’s down to one lane right now; is there an email chain I can be on to know when the lanes will be closed prior to 9pm on Fridays (once again, it’s 8:15pm on a Thursday, and I’m a little irked by this)? Best of luck to complete this project safely and rather quickly (hopefully before the intended end date). Best, Katie link

    Hello! I have basically no issues with this project, but I do have one gripe (likely due to my lack of sleep and growing lack of patience as I sit in traffic). I live two block up from the end of the bridge on 9th Ave. I knew bridge traffic started at 9pm, so I thought I was fine to go across the bridge instead of taking an alternative route that would’ve taken me long to get home. However, I’m now wishing I did the opposite, as I’ve been sitting in traffic since 7:15, and it is now 8:15. I get work needs to be done to keep the bridge safe, but I feel as though it might be helpful to increase times on green lights heading towards the Waterfront area. Also, it’s not 9, so I’m not sure why it’s down to one lane right now; is there an email chain I can be on to know when the lanes will be closed prior to 9pm on Fridays (once again, it’s 8:15pm on a Thursday, and I’m a little irked by this)? Best of luck to complete this project safely and rather quickly (hopefully before the intended end date). Best, Katie

    Katie asked about 1 month ago

    Hi, Katie,

    I’m not sure how we missed this inquiry when you sent it last month. But we did, and we’re sorry for the delay in our response.

    Homestead Borough is responsible for the traffic signals, including their timing, on the Waterfront side of the bridge. Our project team discussed with the borough the possibility of adjusting the timing of the lights, and as a group, we decided that it would potentially create more problems that it would solve. So, the timing remained as usual.

    Regarding when the bridge work starts and stops, our contractor works from 9 p.m. on Fridays through 6 a.m. on Mondays. There were two weeks when there were exceptions. One time we worked on a Wednesday night, and twice we worked Thursday night and during the day on Friday. Those exceptions were due to cold temperatures affecting the curing time of an epoxy overlay on the bridge deck.

    There also was some confusion with the TV news and the public regarding a nearby project. When our bridge project began, Pittsburgh Water was continuing to restrict a lane of traffic at the end of the Pittsburgh side of the bridge for a sewer pump replacement project. While the lane closures were near each other, those two projects were not related. Pittsburgh Water has since completed that project.

    Let us know if you have any additional questions.